SpaceX Data Centers Are Outpacing Big Tech Builders

SpaceX data centers are appearing far faster than anything the biggest US tech companies are building, according to a pointed new analysis of the AI infrastructure race. Its core claim is that Microsoft, Apple, Google, Amazon and Meta have plenty of money but little urgency, and that a rocket company is filling the gap.

The piece is opinion, and its tone is deliberately provocative. The figures behind it are still worth setting out.

Memphis in months

Until mid-2024, xAI had never constructed a data center. Then it converted a vacant factory in Memphis and had 100,000 H100 chips working as one system after 122 days. The grid offered only 7 MW at first, so the team generated its own power. A further 92 days doubled the count to 200,000 GPUs.

Colossus 2 began in March 2025. When local turbine rules got awkward, the power plant went just over the border into Mississippi. The outcome was the first AI training cluster at gigawatt scale, and the Memphis site is heading toward 2 GW. Because xAI joined SpaceX in February 2026, the analysis credits the work to SpaceX.

Stick figure poking something with a stick: "C'mon, do something..."
Image: blog.caseyhandmer.com

A rival leases the old cluster

Anthropic, which buys a lot of Google Cloud TPU capacity, rented all of Colossus 1 in May. That was over 300 MW and 220,000 GPUs, running within a month. SpaceX had already shifted its own training to Colossus 2, and the arrangement later grew to include newer hardware.

Colossus 3 is a converted 810,000-square-foot warehouse in Southaven, Mississippi. Grok-5 now trains across the second and third sites, which together hold 770,000 GPUs and a 1.2 GW gas plant. A fourth Memphis facility is confirmed. On November 12, SpaceX also revealed a $50 billion campus in Cochise County, Arizona, planned for up to 6 GW.

Grim reaper meme: CLPS has already been through the doors labelled Masten, Intuitive Machines and Astrobotic, leaving blood, and knocks on the door labelled Firefly
Image: blog.caseyhandmer.com

Brownsville shows the style

In Brownsville, Texas, SpaceX promised as much as $220 million toward water systems if the city gave up 444 acres quickly. The city did, and Starbase absorbed the land in September. SpaceX intends to build and run a $24 billion, 750 MW gas plant and computing campus there.

Not everyone is cooperating. Brownsville froze new data centers for 90 days from November 4, a statewide pause on air permits stalls the plant, and commissioners passed on a hearing about a 10-year tax break.

What Big Tech is doing instead

The comparison the analysis draws is Google’s withdrawal of a $1 billion Indianapolis-area campus in September 2025 after local opposition. Google’s sustainability chief calls transmission the biggest barrier, with utilities quoting waits of four to ten years. The company’s response is a portfolio of nuclear and fusion contracts that mostly deliver power between 2028 and the early 2030s.

Meta’s January announcement covered up to 6.6 GW by 2035, but 2.1 GW of that is existing Ohio generation. Amazon spent $650 million next to a nuclear plant, only to be blocked by regulators from raising its direct supply from 300 to 480 MW. Microsoft’s Three Mile Island restart, 835 MW, isn’t expected until 2027, and its fusion contract with Helion looks doubtful after a spokesperson said the 2028 target will not happen.

Orbit shows the scale of the gap

Google put its first orbital compute satellite up on October 1. Built by Planet and carrying four Trillium TPUs, it has about 1 kW of solar power and works in short bursts. It flew on a SpaceX rocket. By comparison, SpaceX’s Starlink fleet of more than 11,000 satellites generates about 100 MW. The author calls that a difference of six orders of magnitude.

What to watch next

The author also argues that the wider US launch industry is unhealthy and that SpaceX’s plan to retire Falcon in three years worries insiders. Treat those as the author’s judgments, not established facts.

Concrete markers are easier to follow. Look at Brownsville’s permits, the December 16 vote on Meta’s remaining Louisiana gas plants, and whether any big cloud company commits to orbital compute beyond Google’s two planned 2027 satellites.

Source: blog.caseyhandmer.com

Written by

Saksham Bhargava

Saksham Bhargava runs Alteroid and has been writing about consumer technology for over five years, covering iPhone, Android, Windows, AI tools and gaming. With an MCA and six years of hands-on web development experience, he tests the features he writes about on his own devices and focuses on clear, practical guides that solve real problems. Away from the screen, he enjoys travelling to places most tourists skip.