Bitcoin mining AI leases are now worth far more per megawatt than the mining itself. Core Scientific bills more than $700 million a year, about $1.4 million per megawatt, to host AI computers at sites that once mined bitcoin. A mid-efficiency mining fleet earns roughly $700,000 per megawatt a year before costs.
That gap explains why listed miners keep signing multi-decade data center contracts.
What a megawatt of mining earns now
On November 23, 2026, hashprice, the daily revenue per unit of mining power, stood at about $29 per petahash per day. In June it had dropped to just under $28, an all-time low.
The April 2024 halving cut the block subsidy from 6.25 bitcoin to 3.125, and transaction fees stayed under 1% of block rewards for much of 2026, so they haven’t filled the hole. A fleet running at about 15 joules per terahash turns one megawatt into about $82 of revenue per megawatt-hour. Over a year that comes to about $700,000, before power, staff or machine replacement.
Texas power priced miners out
A mining machine only runs when it earns more than its electricity costs. In early November that test failed across West Texas. From November 7 to 11, daily average power cost $64 to $122 per megawatt-hour, and evening prices around 9 p.m. hit $500 to $650.
In the two weeks to November 14, power cost more than a 25 joule-per-terahash machine could earn in 45% of West Texas hours. Bitcoin’s difficulty fell 9.13% on November 14, the biggest cut since June. Power prices did about four-fifths of that damage and the bitcoin price did the rest.
Hashrate came back near 1,100 exahashes per second within a day once Texas power eased to $26 to $43 per megawatt-hour. Miners switch off when power is dear and return when it’s cheap. An AI hall can’t work that way.
The bitcoin mining AI leases stacking up
Most of these deals are colocation: the landlord supplies the building, grid connection and cooling, and the tenant brings the computers. Many are triple-net, so the tenant also pays taxes, insurance and often electricity.
- Core Scientific billed 485 megawatts in the third quarter, with $215 million of colocation revenue out of $233 million in total. CoreWeave rents about 590 megawatts, and a 15-year, roughly 530-megawatt AMD deal signed July 27 brings its leased capacity to about 1.1 gigawatts.
- TeraWulf signed a 20-year, 401-megawatt lease with Anthropic in Kentucky, expecting about $19 billion over the initial term.
- Riot Platforms has a 20-year, 191-megawatt lease at Rockdale, Texas, worth about $9.1 billion.
- Hut 8 reports about $26.6 billion of base-term contract value, including a 245-megawatt Fluidstack lease backed by Google.
- Cipher Mining has a roughly $5.5 billion, 300-megawatt deal with Amazon Web Services, and CleanSpark has a 20-year, 175-megawatt lease in Georgia.
IREN took a different route. It signed a $9.7 billion, five-year GPU cloud contract with Microsoft and agreed to buy the Nvidia chips from Dell for about $5.8 billion. Owning the chips raises revenue per megawatt, and also the capital it has to put up.
Why former mining sites win AI tenants
The scarce asset is a live grid connection. ERCOT told Texas senators in April that it was tracking about 410 gigawatts of large-load requests, roughly 87% of them data centers. The US Department of Energy says transformers and substation parts now carry lead times of two years or more, and some transformer prices have risen 4 to 9 times in five years.
A site that’s already energized skips that queue. Its land is cleared, its high-voltage line is in and its interconnection agreement exists.
Uptime matters too. Riot’s Rockdale hall is Tier 3, with redundant power and cooling for near-continuous operation. Mining doesn’t need that, since the work can stop and restart without ruining a product.
What’s left for bitcoin
Hashrate peaked near 1,160 exahashes per second in October 2025 and sat at 1,033 exahashes on November 23, 2026. Difficulty adjusts every 2,016 blocks, about two weeks, so remaining miners earn a bigger share when machines leave.
Bitcoin mining AI leases won’t end mining, but expect it to drift toward power an AI tenant won’t take: interruptible grid service, surplus overnight wind and remote generation that can’t promise Tier 3 uptime. Most of the large leases haven’t started billing yet. Core Scientific is the exception, and the rest ramp up between 2026 and 2028. Once a hall is leased the rent is contracted, while hashprice is a daily auction that gets squeezed by a halving every four years.
Source: X (formerly Twitter)