The SB Energy IPO now has a major anchor: Nvidia has committed $3 billion to the SoftBank-backed data center and power developer. An amended registration statement filed with the SEC on Thursday revealed the deal. The shares are slated to list under the ticker SBE on the Nasdaq Global Select Market and Nasdaq Texas.
How Nvidia’s $3 billion is structured
The $3 billion splits into two $1.5 billion pieces. One is a private placement of non-voting Class N common stock, priced at the IPO price. The other is a prepaid forward contract Nvidia paid for on August 17, which gives it Class N shares at a 10% discount to that price.
The listing can go ahead even if neither Nvidia deal closes. Share count and price range are still blank in the prospectus. SoftBank holds on to voting control, so SB Energy will count as a controlled company under exchange rules, but the size of SoftBank’s stake after the offering isn’t stated.

8.8 gigawatts contracted, none running
Customers have signed up for 8.8 gigawatts of critical IT capacity across the portfolio. At the end of September, zero gigawatts were running. Every project still needs to be built and wired to the grid.
Roughly 803 megawatts is being built in Texas:
- 50 megawatts at the Cosmos Research Campus in Travis County.
- 308 megawatts at Milam County 1.
- 445 megawatts at Milam County 2.
The other 8 gigawatts sits at PORTS-Pike, a planned campus in Pike County, Ohio. It would hold 17 buildings and pull about 10 gigawatts from the grid.
The power question in Ohio
A U.S.-Japan partnership announced on its own envisions around 9.2 gigawatts of gas-fired plants beside the site. A SoftBank affiliate outside SB Energy would operate them for a U.S. Commerce Department investment vehicle and an entity created by the Japan Bank for International Cooperation.
Permits haven’t been granted, and no binding agreement with a government body covers the plants. Should they slip, SB Energy says it might have to find power elsewhere. The company calls the speed of getting power online the deciding factor in data center projects.
On the generation side, it runs about 2.2 gigawatts of solar and battery storage today.
Financials behind the SB Energy IPO
Through the first nine months of 2026 the company took in $177.1 million and lost about $1.9 billion. Two items explain most of that: $1.2 billion from revaluing warrant liabilities and $593.6 million in stock compensation. Strip them out and the loss is $117.3 million.
Backlog dwarfs current sales at about $439 billion. Data centers account for roughly $430 billion and the stand-alone power unit for about $10 billion, with PORTS-Pike contracts making up most of the data center share. Backlog counts expected revenue from signed, binding contracts, and the company cautions that delays, changes or cancellations could shrink it.
The September 30 balance sheet shows about $4.5 billion of outside debt after issuance costs and discounts, of which roughly $1.2 billion is due within a year. SB Energy also owed its parent, SBE Global, LP, $709.5 million on revolving notes. Unfinished construction was carried at $5.1 billion.
Why the filing matters
Put side by side, the numbers describe a company that is mostly a promise so far. It has solar and battery assets in service, a long list of signed customers and billions tied up in half-built sites, but no data center capacity online.
For investors, that makes the offering a bet on execution rather than on current earnings. The questions are whether Texas projects totaling 803 megawatts reach customers on schedule, whether the Ohio campus gets its power, and whether $5.1 billion of construction spending turns into lease revenue before debt payments come due.
The gap between $177.1 million in revenue and a $439 billion backlog is the central fact investors will weigh. Almost all future revenue depends on construction, permitting and contract assumptions. Nvidia’s money signals that a major chip supplier wants these campuses to exist, and it adds funding at a stage when the company is carrying $5.1 billion of unfinished construction.
What happens next for SBE
First the company has to fix a price range and share count and win SEC clearance. Nvidia’s placement should close at or just before the offering if its conditions are met. After that comes the real work: finishing the first data centers, hitting lease milestones and starting to book revenue under its contracts.
Source: American Buildout