AWS finance chief John Felton says Amazon’s AI spending plan rests on one rule: commit early to what takes years to secure and buy everything else as late as possible. With AWS AI spending running ahead of proven demand, the approach decides how much risk Amazon carries if AI demand comes in below plan.
Felton laid out the thinking at a September staff meeting and again in later comments. His starting point is blunt: any single-number forecast will miss, and he thinks planning at AWS is too slow and too sequential.
Why one demand estimate isn’t enough
Felton wants finance teams to model stronger and weaker demand side by side instead of betting on a single number. Planning, he said, needs to run much closer to real time.
His rule of thumb is simple. Land, power and permitting take years, so AWS commits to them early. Everything that can be bought later is bought later, because waiting buys information. If customers don’t show up, AWS simply doesn’t order.
He describes the aim as deciding at the last responsible moment.
The numbers behind the bet
Felton points to customer commitments as the clearest demand signal. Signed cloud contracts waiting to be delivered stood at $578 billion at the end of the third quarter, and that backlog is growing at a triple-digit rate. Revenue has accelerated for six straight quarters and most recently grew 39% to $46 billion.
Amazon’s latest quarterly filing adds another figure: $159.6 billion of long-term purchase commitments for property and equipment that haven’t hit the balance sheet yet. Nearly $64 billion of it falls due in 2027. The filing doesn’t split out how much is AWS or AI.
Felton also argues the payoff reaches past AI products. Customers that already keep applications and data on AWS tend to run their AI workloads there too, which lifts demand for compute and storage across the business. “That is the flywheel,” he said.
Cutting the cost of each data center
“The math is hard,” Felton told colleagues, asking how AWS can know whether it’s the lowest-cost provider. His answer is to give the company more ways to add capacity instead of one large commitment years ahead.
Prasad Kalyanaraman, an AWS infrastructure leader, described work on more data center layouts and server setups to choose from. Felton likes that because AWS wouldn’t have to pay three years ahead on a guess.
The same scrutiny reaches small parts. In a recent buying round for power-distribution cabinets, AWS looked at each supplier’s factory output and exposure to tariffs as well as price. One outcome was an internal review of a possible deal with manufacturer Jabil that could cut annual costs by $300 million.
- Project Houdini moves parts of construction into factories with a modular design.
- Project Titus reworks facilities to fit denser AI hardware while trimming power and cooling bills.
Timing still slips. AWS began receiving billions of dollars of Nvidia equipment before some data centers had enough power, and racks sat in intermediary warehouses. An AWS spokesperson called staging servers ahead of deployment standard practice.
Lessons from the pandemic retail build-out
Felton spent roughly two decades at Amazon before moving to AWS in 2024, much of it on the retail and delivery network. He joined the company’s senior S-team, which includes CEO Andy Jassy, in 2020.
During the pandemic Amazon rushed to add warehouses, shipping capacity and staff. Growth later slowed and the company had too much warehouse space. In a 2022 internal email, Felton warned that costs would stay a problem until demand caught up with that extra capacity.
A former Amazon executive said he pushed teams to show how plans would hold up if demand weakened. The person called him anything but cavalier and said he insists on data behind the numbers.
Felton later helped regionalize the US delivery network, moving inventory closer to customers. Retail chief Doug Herrington credited him and his team with faster delivery and lower costs when his move to AWS was announced.
When speed is worth paying for
Caution doesn’t always mean spending less. A former AWS executive said the company spent about $100 million, roughly two years ago, to bring one data center project forward by six to nine months. Felton made teams justify the faster timeline, and AWS approved it because capacity online sooner mattered more.
What to watch next
The next test is whether backlog growth keeps pace with the build-out. If AWS contracts stay ahead of what it can install, Felton’s staged approach looks cautious but sound. If demand cools, the early commitments on land, power and permits are the ones Amazon can’t cancel.
Felton’s own position hasn’t wavered. “Speed is a choice,” he said, and for AI his answer is to move fast.
Source: Business Insider