Applied Digital (NASDAQ: APLD) has signed a new 18-year lease with an investment-grade hyperscaler for 150 MW of critical IT capacity. The Applied Digital lease brings in about $5.4 billion of base-term contracted revenue. It pushes the company’s total contracted base-term lease revenue past $41 billion.
The company announced the deal on November 23, 2026. It didn’t name the tenant, describing it only as a tier-one, investment-grade hyperscaler.
The numbers behind the deal
The base term is 18 years. If the tenant uses every renewal option, the term stretches to 33 years and the lease is worth about $12.7 billion.
The same logic applies to the whole portfolio. Contracted base-term revenue stands above $41 billion, and it would reach roughly $100 billion if every renewal option across all leases is exercised. Renewals are the tenant’s choice, so the larger figure is a ceiling and not a commitment.
Applied Digital says this lease carries better commercial terms than its earlier ones, including higher pricing. The company also points to the 18-year length as a source of longer revenue visibility.
A portfolio now past 1.6 GW
With the new agreement, Applied Digital has more than 1.6 GW of contracted critical IT load and 2.2 GW of grid-connected peak load. About 75% of its contracted base-term lease revenue now comes from investment-grade customers.
Applied Digital designs, builds and operates large AI data center campuses and leases them to hyperscale customers on long contracts. Its pitch is a mix of real-estate economics and the specialized needs of AI computing, such as power, advanced liquid cooling and connectivity.
CEO Wes Cummins said the lease reinforces the company’s customer relationships and the quality of its contracted revenue, and that the focus stays on executing with speed and consistency.
How the build will be paid for
Chief financial officer Saidal Mohmand laid out the financing plan. It starts with first-in equity already funded from the balance sheet and a $5 billion programmatic equity partnership with Macquarie Asset Management. Project financing backed by the long-term lease follows.
The timeline for that debt is specific:
- Delta Forge 1 and Polaris Forge 3: remaining project finance expected in the first calendar quarter of 2027
- Delta Forge 2: expected in the second calendar quarter of 2027
Mohmand said the approach is meant to lower the cost of capital while matching spending to construction timelines.
Why long leases matter for AI data centers
Building a campus for AI workloads takes years and a lot of capital before a single server runs. A tenant that commits for 18 years gives lenders something concrete to underwrite, which is why the financing plan leans on the lease itself.
It also explains the company’s emphasis on credit quality. When three quarters of contracted revenue comes from investment-grade customers, project debt is easier to arrange on reasonable terms, and Applied Digital argues that supports its long-term leasing model.
The flip side is concentration. The company’s disclosures say it depends on principal customers, so a problem with one large tenant would weigh heavily on results. The unnamed hyperscaler here is another large commitment in that pattern, and the market has no way yet to judge how it compares with earlier tenants.
When the capacity arrives
Delivery is expected to begin in the first half of calendar 2028. That date depends on development milestones, utility arrangements and regulatory approvals.
Those conditions matter. The company’s own risk disclosures list completing construction as planned, securing power supply agreements and raising enough capital among the factors that could change the outcome. They also name its dependence on a small group of principal customers.
The catch for anyone reading the headline revenue figure is timing. Nothing in the Applied Digital lease pays out at full scale until the buildings are finished and powered. Investors will watch the financing closes in early 2027 as the first real test, and the 2028 delivery window as the second.
Source: Applied Digital Corporation